| № | Entity | Function | Maximum period |
| 1 | Legislative Assembly of the Kirov oblast. | Ratifies the oblast Law of the Oblast Budget for the corresponding fiscal year (or amendments to it), alloting funds for the state support for the investment activities on the territory of the oblast | |
| 2 | The oblast Government | makes decisions and authorizes the Consultative board to run a competition for the state support among the investment projects (business-plans) to be realized in the high-priority industries of the oblast's economy | 30 days |
| 3 | The Consultative board for investment policy with the Government of the oblast | Aproves the competition documentation and sets time terms of running the invetsment projects (business-plans) competition. | 30 days |
| 4 | Department of Economic development with the Government of the oblast | announces in the media of the competition among the investment projects (business-plan) | 10 days |
| 5 | Private investors. Contenders | They submit a set of competition application documents to the Department of Economic Development wit the oblast Government in order to get state support. | 30 days |
| 6 | TheDepartment of Economic development with the oblast Government is an executive body of the Consultative board for the Investment policy with the Government of the oblast | checks on the completeness of the set of the documents; registers the investment projects (business-plans) and transfers the documents to the executive body of the corresponding industrial branch for technical and economic assessment. | 5 days |
| Executive bodies of the corresponding industrial branches of the Kirov oblast. | perform technical-and-economic assesment of the invetsment projects and transfer the documentation back to the Department of Econimic Development | 10 days |
| Department of Econimic Development with the
oblast Government | performs comprehensive assesment of social-econimic efficiency of the investment project (business plan); draws a list of the submitted investment projects (business plans) and a set of documents required for the consideration by the Consultative board | 15 days |
| Consultative board for the Invetsment Policy with the oblast Government | performs selection of the projects liable for state support based on the projects' compliance with the guidelines of the oblast's economic development.
| |
| 7 | Department of Econimic Development with the
oblast Government | prepares the draft of the oblast Government decree of approval of the list of the high-priority investment projects - competition winners - liable for state support from the funds of the oblast budget. | 15 days |
| The oblast Government | approves the list of the investment projects (business-plans) | |
| 8 | Department of Econimic Development with the
oblast Government | issues written notifications: | |
| | to the winners of the investment projects (business-plans) competition. | 3 days |
| | to the rest of the contenders of the investment projects (business-plans) competition. | 10 days |
| | tomass media to spread the news of the results of the investment projects (business-plans) competition.
V | 20 days |
| 9 | The oblast Department of Finance and private investors - the winners of the investment projects (business-plans) competition | According to the oblast Government decree of approval of the list of the winners of the investment projects (business-plans) competition and draws an agreement of state support granting | 20 days |